Coppola Services worked with Western Monmouth Utility Authority on a complete reconstruction of five pump stations throughout a large collection system, ranging from flows of 0.25 MGD to 2.0 MGD.
All existing flows were maintained via bypass pumping systems and temporary controls. Each site consisted of new wet wells ranging in depths from 18ft to 27ft and all required dewatering during construction.
New precast concrete control buildings were installed at each site with exterior designed to blend in with the existing community.