Borough of Freehold Water Treatment Plant

Coppola Services was awarded the contract as the prime contractor for the construction of a ground up, new 3 MGD water treatment plant to replace an existing treatment plant that has reached the end of its useful life.

  • Customer: Borough of Freehold
  • Budget: $7.8 Million
  • This project consisted of the complete construction of a new water filtration plant capable of treating 3.3 million gallons of drinking water per day fed from six ground wells on site.

    Project Scope:

    • Construct new block and brick building, with metal trusses and shingle roof, domestic and sanitary plumbing, HVAC and fire protection sprinkler system
    • Erect bolted steel clarifier tank with sloped concrete floor for backwash waste settling, along with precast wet well, valve and meter chamber for force main
    • Install and start up three pressure-filter tanks, two submersible pumps, two centrifugal pumps, and one air blower, four chemical feed systems and 48” chlorine contact chamber, all complete with pipe, fittings and valves
    • Complete automatic controls with new SCADA system and cellular LAN including new water tower control panels